Mount Avoca Winery

Mount Avoca Winery

Avoca

Solar Panel & Inverter Installation in Avoca by Energy Reset

46 kW Solar + 48 kWh Battery | Whole-Site Energy Management

Mount Avoca already had a 30 kW solar system installed in 2016, but there was a problem: the system was connected to the shed sub-board and could primarily offset the energy used in the shed where the wine production took place.

The estate’s electricity consumption extended well beyond the shed. The property also included eco lodges, water pumps, offices and reception facilities, all supplied from the main switchboard approximately 105 metres away.

The objective was to make the solar energy work for the entire estate, rather than just one part of the property.

Energy Reset added a 46 kW solar system and 48 kWh Sigenergy battery, while integrating the existing solar system into the site’s broader energy management setup.

A key part of the project was installing data cabling between the systems and the main switchboard, along with wireless CT sensors to accurately measure the estate’s overall consumption. This allowed the solar and battery system to respond to energy demand across the property.

The project also included blackout protection for the office and reception, providing additional resilience when grid power is unavailable.

What initially looked like a straightforward solar expansion required careful system design, long-distance communications infrastructure and integration with an existing solar installation.

The result is a whole-site energy system designed to maximise the value of solar and battery storage across the entire estate.

Existing solar: 30 kW
New solar: 46 kW
Battery: 48 kWh Sigenergy
Key feature: Whole-site energy monitoring and blackout protection